firewood, briquettes, pellets and wood chips, coal (backup)
TМ-100…3000
Capacity: 100 to 3000 kW
ARDENZ solid fuel three-pass fire-tube hot water boilers with capacities from 100 to 3000 kW.
Series T features manual fuel loading, while series TM is equipped with mechanized fuel feeding.
The boilers are equipped with an efficient three-pass heat exchanger, ensuring high efficiency and stable operation. The design includes a heat-resistant combustion chamber, full thermal insulation, and the possibility of automation (cleaning, fuel supply).
They operate on firewood, briquettes, pellets, and wood chips (coal — as backup fuel). An optimal solution for industrial and municipal facilities, including integration into modular boiler units.
Application areas:
based on Т/TM
Primary and backup MBU
from 100 to ∞ kW
firewood, briquettes, pellets and wood chips
The modular boiler unit is designed for heat generation and distribution for industrial and municipal facilities.
It features a mobile design, easy connection to utility networks, and remote control capability. Supplied as a complete solution and ready for operation after installation.
Our production is fully certified. Every year, our products and solutions undergo certification in accordance with Ukrainian regulatory requirements.
Implemented projects based on Т/ТМ
solid fuel fire-tube hot water boiler ARDENZ TM 800 – 1 unit
800 kW
wood chips
Modular Boiler Unit (MBU)
The boiler house consists of one transportable module, ready for connection to the network after installation on a prepared site. The module is fully equipped with all necessary equipment for operation of an 800 kW boiler house.
Project of the Ministry of Defence of Ukraine (Zhytomyr Housing)
December 2022
solid fuel water-tube hot water boilers ARDENZ TM 10,000 – 2 units
20 000 kW
wood chips
Modular Boiler Unit (MBU)
The boiler house consists of generating, process, and auxiliary modules, ready for connection to the network after installation on a prepared site. The modules are fully equipped with all necessary equipment for operation of a 20 MW boiler house.
Rivne, Rivne region
April 2022